Hospital Commissioning Checklist: The Final 90 Days
A hospital commissioning checklist helps you check whether your new hospital is ready to receive patients. Completed interiors, installed equipment and an inauguration date are only part of the picture. Your people, approvals, utilities and everyday processes must work together.
The final weeks bring many decisions: which departments can open, who will cover each shift, whether essential systems have passed their checks, and what must be resolved before the first admission. A structured plan gives each task an owner, a deadline and evidence of completion.
Start the planning much earlier.
The 90-day schedule below is a suggested management framework, not a statutory deadline or a promise that every project can open within three months. Design, approvals, utility connections and long-lead procurement may need to begin well before this period.
1. Define What Will Open on Day One
Confirm the opening bed strength, specialties, procedures and operating hours. Identify the support each service needs, including diagnostics, pharmacy, emergency response and referral arrangements.
For example, a project may be designed for 50 beds but initially open 25. This is an illustrative planning choice, not a recommended bed number. The first phase still needs the staffing, infrastructure and permissions appropriate to its services.
Record which areas will remain closed and how they will be separated from patients, staff movement and unfinished construction. Match your website, signage and launch announcements to the services actually available.
2. Your 90-Day Hospital Commissioning Checklist
Appoint one commissioning coordinator. Clinical, nursing, engineering, biomedical, HR, IT and finance leads should each own their tasks. Use this timeline to organise reviews, adjusting it to the project’s dependencies.
| Period | Main focus | Review evidence |
|---|---|---|
| 90–61 days before | Confirm opening scope, approval gaps, recruitment and delivery schedules. | Department plan, responsibility list and unresolved dependencies. |
| 60–31 days before | Complete installations, recruit teams, configure software and prepare procedures. | Test schedules, joining dates, operating procedures and service contracts. |
| 30–8 days before | Train staff, run simulations, check supplies and resolve failures. | Training records, drill findings and successful retests. |
| Final 7 days | Confirm permissions and readiness for each proposed service. | Documented opening decision, restrictions and escalation contacts. |
Review progress weekly, then more frequently as opening approaches. Keep unresolved items visible even when a vendor describes a package as “completed.”
3. Check Approvals Against the Actual Services
Create an approval register showing the requirement, responsible authority, application status, inspection needs, conditions and validity. Record the evidence needed before each service begins.
Hospital registration requirements depend on the state or union territory. The central Clinical Establishments Act does not apply uniformly across India; confirm the framework applicable to your location with the relevant authority.
- Review applicable building use, occupancy and fire requirements.
- Check the registrations and permissions relevant to the hospital and its proposed services.
- Confirm requirements for pharmacy, biomedical waste, diagnostic imaging and other specialised facilities, as applicable.
- For diagnostic X-ray services, verify the requisite AERB consents and permission to operate before patient use.
An application acknowledgement should not be treated as permission to begin a service. Record exactly what has been authorised and what remains outstanding.
Official references: Clinical Establishments Act FAQs and AERB diagnostic radiology requirements.
4. Verify Engineering and Equipment Readiness
A delivery note confirms that an item arrived. Commissioning also needs evidence that it is installed correctly, works with its supporting services and can be used by trained staff.
- Engineering systems: obtain documented checks for electrical supply, backup power, water, lifts, fire systems and other relevant utilities.
- Clinical infrastructure: have qualified specialists verify applicable medical gas, ventilation and other service-specific systems.
- Medical equipment: complete acceptance checks, required calibration or quality assurance, and user training.
- Operating support: confirm accessories, compatible consumables, maintenance contacts and breakdown response arrangements.
- Handover: collect manuals, drawings, test reports, warranties, asset records and outstanding-defect lists.
Test interfaces as well as individual items. A functioning monitor does not prove that the room’s electrical backup, alarms or staff response arrangements are ready.
5. Prepare the People and Patient-Care Processes
Convert recruitment numbers into workable duty rosters. Confirm joining dates, credentials, responsibilities, clinical privileges where applicable, shift coverage and escalation arrangements. Include leave and absence cover.
Train teams on the workflows they will use: patient identification, assessment, consent, medication handling, transfers, documentation, discharge and emergency escalation. Clinical leaders should approve procedures appropriate to the services being opened.
Infection prevention must be operational.
Check hand-hygiene facilities, cleaning responsibilities, protective supplies, waste segregation and safe handling of reusable equipment. Where relevant, verify sterilisation arrangements and clean-to-dirty workflows. Assign an infection-control lead and train staff before patient services begin.
Reference: NCDC National Guidelines for Infection Prevention and Control in Healthcare Facilities, January 2020.
6. Test IT, Supplies and Commercial Readiness
Configure the hospital information system using the actual opening departments, doctors, beds, tariffs and user roles. Test a complete transaction before relying on it during patient care.
- Patient records: check registration, identification, access permissions, documentation and retrieval.
- Billing: verify consultations, investigations, medicines, deposits, refunds and discharge bills.
- Downtime: prepare a usable process for software or network failure and test backup restoration.
- Supplies: confirm opening stock, storage, expiry checks, reorder responsibility and supplier delivery arrangements.
- Cash requirements: plan funds for payroll, utilities, supplies and other near-term payments after opening.
Verify the activation status and terms of insurer, TPA and corporate arrangements. Communicate cashless availability only where it is confirmed for the relevant service and payer.
7. Run Simulations Before Receiving Patients
Use staff acting as patients and dummy records to test the full journey. Keep test records separate from live clinical and billing data.
Example admission simulation
Arrival → registration → assessment → admission decision → bed allocation → nursing handover → investigation orders → medication workflow → discharge documentation → final billing.
Run relevant emergency, fire, evacuation and utility-failure drills under qualified supervision. Include staff from different shifts and outsourced teams whose response affects the hospital.
For every failure, record what happened, who will correct it and when it will be retested. A drill attendance sheet alone does not show that the problem was resolved. Do not use real patients to discover whether an unverified essential system works.
8. Make a Documented Opening Decision
Bring the promoter, medical leadership and responsible department heads together for the final readiness review. Each opening service should have evidence covering:
- Applicable permissions and conditions confirmed.
- Safe premises and essential utilities verified.
- Equipment accepted and users trained.
- Staff and escalation cover available for the advertised hours.
- Supplies, pharmacy and diagnostic support arranged.
- Clinical, infection-control and emergency procedures implemented.
- IT workflows and downtime arrangements tested.
- Critical drill findings closed and retested.
Use clear status labels: Ready, Action pending or Hold. Every outstanding item needs an owner, deadline and assessment of its effect on opening.
A percentage score must not decide patient readiness.
A department can complete most checklist items and still have one unresolved safety or licensing issue that prevents it from opening. Hold the affected service until the issue is resolved. A phased launch must also meet shared building and hospital-wide requirements.
Record the authorised service scope, opening hours, remaining restrictions and named decision-makers. Let this review determine the patient-service opening date.
9. Plan the First 30 Days After Opening
Keep the commissioning team available as real workflows settle. Start with short daily reviews of incidents, equipment downtime, staffing gaps, stock availability, billing problems and patient feedback.
Assign corrective actions and check whether they worked. Review each additional department before expanding services; readiness in one area does not automatically establish readiness elsewhere.
Frequently Asked Questions
When should hospital commissioning planning begin?
Begin during project planning so that design, procurement and staffing support the intended services. The final 90 days are a useful coordination window, but some activities require a much longer lead time.
Can a new hospital open in phases?
A phased opening may be feasible when the relevant permissions allow it and each opening service has its required support. Confirm shared dependencies, safe separation from unfinished areas and the effect on emergency arrangements.
Who should sign off the hospital commissioning checklist?
Assign sign-off to the accountable hospital leadership and relevant clinical, engineering and operational specialists. Their internal review does not replace approvals or certifications required from competent authorities.
Related Reading for New Hospital Projects
Preparing to Open Your New Hospital?
HOSCONS supports hospital promoters with commissioning planning, manpower planning, recruitment support, SOP development and operational readiness.
Share your project location, proposed opening beds, specialties, current stage and target opening date to discuss the support your hospital needs.
Explore our new hospital project services
Email:
grace@hoscons.com